Albion Path Team Update

July 23, 2026, Paul Wyntergreen, Team Coordinator


The Team is wrapping up the last detail comments to finalize the Conceptual 10% Design Plan Set being prepared by DOWL Engineering under a Tillamook County Transient Lodging Tax grant. The OAP should be receiving the final set in August for use in pursuing subsequent grants for any one (or combination) of the 8 path segments.


The final set will contain rough designs on an aerial for each segment of the pathway, indicating widths, materials, and which side of the road it is on, along with crosswalk, flashing beacon, and retaining wall locations. There will also be a cost estimate for each segment, adjusted over time for inflation, that can be used for grant requests.


The Team's next focus will be researching impending grant opportunities for full engineering, and eventually construction, on a segment by segment basis.


July 13, 2026
Improving Cell Reception Team Update July 13, 2026 by Yuriy Chanba, Team Coordinator
June 28, 2026
Roads and Parking Team Update June 27, 2026, David Dulaney, Team Coordinator
June 1, 2026
Albion Path Team Update May 29, 2026, Paul Wyntergreen, Team Coordinator
More Posts